Turning Around Troubled ERP Implementations

  1. Introduction

Enterprise Resource Planning (ERP) implementation is among the most ambitious undertakings an organization can attempt. Unlike localized IT initiatives, ERP transformation spans every business process, from finance and supply chain to customer service and human resources. It integrates data, people, and technologies across departments, aiming to create a single source of truth.

Yet, history shows that ERP projects are prone to challenges. Studies suggest that over 50% of ERP implementations exceed budgets and timelines, while as many as one in five are considered outright failures. When projects derail, the consequences extend beyond financial loss: business operations suffer, employee morale declines, and leadership credibility is questioned.

This consulting note outlines the root causes of ERP failure, provides a structured approach to turning around troubled projects, and offers a framework for re-implementation that maximizes prior investment while restoring confidence across stakeholders.

  1. Common Causes of ERP Implementation Failure

Troubles often arise not from technology alone, but from the intersection of people, processes, and governance. Based on lessons learned from numerous ERP engagements, the following areas repeatedly emerge as critical failure points:

2.1 Solution & Vendor Evaluation

  • Selection based on cost or brand reputation rather than alignment with business requirements
  • Over-promising during sales cycles leading to a mismatch between solution capability and organizational need
  • Lack of independent validation of vendor proposals

2.2 Project Organization & Planning

  • Weak governance structure with unclear decision-making authority
  • Incomplete or unrealistic project plans, often underestimating resource requirements
  • Steering committees existing in name only, without active leadership involvement

2.3 Change Management

  • Resistance from employees due to inadequate communication about the “why” behind ERP transformation
  • Insufficient training, resulting in users reverting to legacy systems or workarounds
  • Cultural misalignment, expecting quick adoption where trust in leadership is already fragile

2.4 Expectation Management

  • Executives treating ERP as a pure IT project rather than a business transformation
  • Lack of clarity on what success looks like: operational efficiency, regulatory compliance, data transparency, or all of the above
  • Unrealistic timelines that prioritize speed over quality

2.5 Misalignment of People, Processes, and Technology

  • Business processes forced to fit software rather than software enabling better processes
  • Fragmented processes across departments creating inconsistencies
  • Gaps in integration with critical third-party applications (CRM, HRMS, analytics platforms)
  1. Recognizing a Troubled Project

An ERP project does not collapse overnight; it exhibits warning signs long before failure. Early recognition is key to minimizing loss:

  • Schedule slippage: critical milestones missed repeatedly
  • Budget overrun: escalating change requests and unplanned resource costs
  • Low user adoption: end-users resist system use despite training
  • Eroding stakeholder confidence: sponsors question progress, vendors become defensive, and delivery teams lose morale

When two or more of these red flags occur simultaneously, leadership should initiate a formal project review rather than continuing in denial.

  1. Turning Around Troubled ERP Projects

A troubled project can be salvaged if approached with discipline. The turnaround process is both a forensic analysis and a strategic reset.

4.1 Step 1: Comprehensive Diagnostic Review

Conduct a neutral and independent assessment of the following artifacts and activities:

  • Contracts with implementation partners
  • Solution Design Document (SDD) and Functional Specifications
  • Project Scope, including change history
  • Project Plan (baseline vs. updated versions)
  • Implementation methodology followed to date
  • Project organization, governance records, and communication logs
  • Cost budget vs. actual expenditures
  • Testing strategy and results
  • Available infrastructure
  • End-user training materials
  • Cutover and go-live strategies

4.2 Step 2: Root Cause Analysis

  • Identify systemic issues (e.g., flawed methodology, inadequate vendor competence)
  • Separate correctable process gaps from structural solution mismatches
  • Distinguish short-term fixes from long-term sustainability measures

4.3 Step 3: Stabilize and Contain

  • Stop further scope creep and freeze unnecessary enhancements
  • Realign project leadership and reconstitute an empowered steering committee
  • Re-establish communication channels with users to rebuild trust

4.4 Step 4: Redefine Success and Re-Plan

  • Define measurable objectives (e.g., 20% faster financial close, 15% reduction in inventory carrying cost)
  • Re-plan the project in smaller, achievable phases
  • Establish transparent KPIs to monitor progress.

4.5 Step 5: Execute Re-Implementation

  • Where feasible, reuse prior investments (customizations, training, infrastructure)
  • Introduce new safeguards—clear change control, independent quality assurance, periodic checkpoints
  • Focus first on stabilizing critical business processes before rolling out advanced features

4.6 Framework: The Four-Stage Turnaround Model

  • Assess – Review documents, contracts, and current system
  • Redesign – Align solution with business needs and realistic scope
  • Re-implement – Phase-based execution with checkpoints
  • Stabilize – Embed training, governance, and performance monitoring.
  1. Lessons Learned and Success Factors

ERP turnarounds often reveal recurring lessons, reminding organizations that disciplined planning, realistic expectations, and independent oversight are vital for success:

  • Executive ownership is non-negotiable. Projects fail when left solely to IT
  • Transparency builds confidence. Regular, honest reporting prevents surprises
  • People determine success. Investment in change management and training yields higher adoption than technical fixes alone
  • Independent oversight adds value. External advisors often provide objectivity that internal teams lack
  • Define “minimum viable success.” A phased win is better than chasing perfection and failing completely
  1. Conclusion

ERP projects are high stakes endeavors that test both organizational resilience and leadership. When they falter, the instinct may be to abandon the effort and write off investments. Yet, with a structured turnaround approach, organizations can salvage sunk costs, rebuild stakeholder confidence, and achieve transformative outcomes.

The path to recovery lies in acknowledging failure early, engaging the right expertise, and re-focusing on measurable business value. By converting setbacks into learning opportunities, enterprises can turn troubled ERP implementations into lasting success stories.